| Pothole | Greater than or equal to 40mm deep and at least 200mm wide in all directions | Within 2 hours | 
		
			| Pothole | Greater than or equal to 30mm deep and at least 200mm wide in all directions | Within 5 days | 
		
			| Pothole | Greater than or equal to 20mm deep and at least 200mm wide in all directions | Within 28 days | 
		
			| Joints or cracks – parallel to cycleway | Greater than or equal to 40mm width and greater than 40mm deep. | Within 2 hours | 
		
			| Joints or cracks – parallel to cycleway | Greater than or equal to 30mm width and greater than 40mm deep. | Within 5 days | 
		
			| Joints or cracks – parallel to cycleway | Greater than or equal to 20mm width and greater than 40mm deep. | Within 28 days | 
		
			| Uneven surface | Difference in level greater than or equal to 40mm and at least 200mm in any direction | Within 2 hours | 
		
			| Uneven surface | Difference in level greater than or equal to 30mm and at least 200mm in any direction | Within 5 days | 
		
			| Uneven surface | Difference in level greater than or equal to 20mm and at least 200mm in any direction | Within 28 days |