Woodsgate Park, Bexhill - Footway Resurfacing

A map showing the footway resurfacing extent in Woodsgate Park, Bexhill

A map showing the footway resurfacing extent in Woodsgate Park, Bexhill

Balfour Beatty is working in partnership with East Sussex County Council to manage the highways service across East Sussex. As part of this, we will be carrying out footway resurfacing and other associated works on Woodsgate Park, Bexhill.

The other associated works will include ironwork and kerb adjustments.

What are we doing?

Work will start on Monday 26 June 2023 and continue until Friday 11 August 2023 in the following phases:

Phase 1: Monday 26 June to Friday 7 July - Work will be carried out on the Southern side between Bancroft Road and Down Road. The road will remain open under temporary traffic signals.

Phase 2: Monday 10 July to Wednesday 12 July - Work will be carried out on the Southern side between Down Road and West Down Road postbox. The road will remain open under temporary traffic signals. 

Phase 3: Thursday 13 July to Monday 17 July - Work will be carried out on the Northern side between Gunters Lane and Park Lane. The road will remain open under temporary traffic signals.

Phase 4: Thursday 18 July to Thursday 27 July - Work will be carried out on the Northern side between Park Lane and Gatelands Drive.

Phase 5: Friday 28 July to Wednesday 2 August - Work will be carried out on the Northern side between Gatelands Drive and Old Farm Road.

Phase 6: Wednesday 2 August to Monday 7 August - Work will be carried out on the Northern side between Old Farm Road and Dane Court Close.

How will this impact highway users?

These sections of footway will be closed to pedestrians during the above dates. 

There will be no weekend working and the road will remain open under temporary traffic signals between 7am and 7pm. 

Information for residents and businesses

Parking: We will put out ‘no parking’ signs and cones on the site to advise where parking is restricted. Please avoid parking in these locations as it will delay our works.

Weather: All of these works are subject to favourable weather conditions, for example heavy rain may affect the progress of the works.

Properties close to the carriageway may experience a temporary disturbance as this can be a noisy process and those properties may experience flashing lights and reversing sirens. We would like to take this opportunity to apologise in advance for any inconvenience or disruption this work may cause.