Underhill, Maresfield & Cobdown Lane/Budletts Lane, Uckfield - New signage and posts

Maps of works areas

Maps of works areas

Balfour Beatty is working in partnership with East Sussex County Council to manage the highways service across East Sussex. As part of this, we will be installing new signs and posts on Underhill in Maresfield, and Cobdown Lane and Budletts Lane in Uckfield.  

When do they start?

Works will be carried out on Monday 15 September, between 7am and 7pm

We will inform you of any changes to the dates or times via advanced warning signs on site.

How will this impact highway users?

We will be working in three locations:

  • Underhill: outside ‘Millers Yard’
  • Cobdown Lane: at the junction with the A26 on both sides.
  • Budletts Lane: opposite the junctions by Millwood Lane and Court Lane.

All roads will remain open with minimal disruption to road users while the work is undertaken.

Information for residents and businesses

Parking: We will put out ‘no parking’ signs and cones on the site to advise where parking is restricted. Please avoid parking in these locations as it will delay our works.

Weather: All of these works are subject to favourable weather conditions, for example heavy rain may affect the progress of the works.

Properties close to the carriageway may notice some noise, flashing lights, or reversing sirens. We will do our utmost to keep this to a minimum.

We would like to take this opportunity to apologise in advance for any inconvenience or disruption this work may cause, however this forms part of our continuing improvement for the East Sussex highway network.

Please let us know how we did by leaving feedback. Please note you will be redirected to the East Sussex County Council consultation website.

Feedback Form

One.Network Permit References - EA224-RS0161-UNDERHILL-01, EA224-RS0161-COBDOWN-01 & EA224-RS0161-BUDLETTS-01