Map of works area
Balfour Beatty is working in partnership with East Sussex County Council to manage the highways service across East Sussex. As part of this, we will be carrying out traffic signal works in Sutton Avenue, Peacehaven.
When do they start?
Work will be carried out on Monday 20 January 2025 to Friday 21 February 2025 between 8am and 4pm.
We will inform you of any changes to the dates or times via advanced warning signs on site.
What are we doing?
These works involve removal of the current signals, followed by the installation of new, upgraded traffic signals.
This work forms part of a county wide programme of replacement for sites that have reached the point of uneconomical repair or have parts that can no longer be replaced.
How will this impact highway users?
The team will be working at the ‘T’ junction with Arundel Road West. The road will remain open with temporary traffic lights and a pedestrian crossing in place while the work is completed.
Information for residents and businesses
Parking: We will put out ‘no parking’ signs and cones on the site to advise where parking is restricted. Please avoid parking in these locations as it will delay our work.
Weather: All of these works are subject to favourable weather conditions, for example heavy rain may affect the progress of the works.
Properties close to the carriageway may experience a temporary disturbance as this can be a noisy process. There may also be flashing lights and reversing sirens.
Permit Reference - EA44484772531-02
We would like to take this opportunity to apologise in advance for any inconvenience or disruption this work may cause, however this forms part of our continuing improvement for the East Sussex highway network.
Please let us know how we did by leaving feedback. Please note you will be redirected to the East Sussex County Council consultation website.