Shinewater Bridge, A22 Golden Jubilee Way, Eastbourne

Shinewater bridge map

 

Update: 13 October 2026

We're continuing to make good progress on our bridge maintenance project.

Since temporarily lifting the bridge using specialist jacking equipment, our teams have been carrying out a range of essential repairs that can only take place while the structure is supported. This has included removing ageing components, preparing areas of the bridge for replacement parts, carrying out concrete alterations and installing new bridge bearings.

Bridge bearings are a key part of the structure. They help transfer the weight of traffic safely through the bridge while allowing it to move naturally as temperatures change.

The temporary 40mph speed limit remains in place to support the safe delivery of these works. Lower vehicle speeds help reduce the impact of traffic on the bridge while temporary support systems are being used and provide a safer environment for site teams and construction vehicles accessing the work area.

This essential maintenance will help keep the bridge safe and reliable for the thousands of journeys made across it each day.

The project is expected to continue until January 2027, and the temporary traffic management measures will be removed as soon as they are no longer needed.

Thank you for your patience while we carry out these important improvements.

The old and new bearings

The old and new bearings

'Jacking up' the bridge ready for near bearings

'Jacking up' the bridge ready for new bearings

Update: 19 August 2026

Work is continuing on the Shinewater Bridge improvement project in Eastbourne.

Recently we lifted bridge by a couple of millimetres over three nights, so that worn components supporting the structure can be replaced. This is one of the most important stages of the project and will help extend the bridge's lifespan for years to come.

Although much of the work is taking place underneath the bridge, both the road and the railway line were closed to install the temporary supports required. We also took the opportunity to carry out additional carriageway joint repairs and safety barrier surveys, making the most of the road closure already in place.

Good progress is being made and once complete, the improvements will help ensure Shinewater Bridge continues to provide a safe and reliable connection for Eastbourne residents, businesses and visitors long into the future.

Pre-construction

Pre-construction

Pre-construction

Pre-construction

 

Balfour Beatty is working in partnership with East Sussex County Council to manage the highways service across East Sussex. As part of this, we will be carrying out essential bridge maintenance works on the Shinewater Bridge, Golden Jubilee Way, Eastbourne.  

Once completed, these works will keep the bridge in it’s optimal condition and ensure the bridge remains safe for all users.

When do they start?

Work will be carried out over a period of 10 months, from Thursday 26 March 2025.

We will inform you of any changes to the dates or times via advanced warning signs on site.

What are we doing?

These works involve replacing bridge bearings and joints - vital components that allow the structure to move safely as temperatures change and traffic passes over it. Following detailed inspections, these elements have reached the end of their intended service life and are now being replaced as part of a proactive maintenance programme

How will this impact highway users?

The work has been carefully planned to minimise disruption, particularly given the bridge’s location over the railway and on the A22 into Eastbourne.  The majority of work will be carried out from underneath the structure with the road staying open to traffic.

There will be an overnight lane closure in place for one night on Thursday 26 and Friday 27 March to allow for the speed limit reduction to be installed.

The speed limit reduction will be in place until the works are completed in January 2027 for the safety road users and our team.

There will also be overnight lane closures in July and October 2026 to allow for the bridge to be raised and lowered safely, along with lane closures for the replacement of joints. Further information will be provided on this webpage and our social media channels.

Information for residents and businesses

Weather: All of these works are subject to favourable weather conditions, for example heavy rain may affect the progress of the works.

We would like to take this opportunity to apologise in advance for any inconvenience or disruption this work may cause, however this forms part of our continuing improvement for the East Sussex highway network.

Please let us know how we did by leaving feedback. Please note you will be redirected to the East Sussex County Council consultation website.