Planned Maintenance Programme 2024-25

The below shows current scheduled dates for planned maintenance in the 2024-25 financial year.

Please note that this programme is subject to change at short notice as these activities are weather dependent. 
Local residents and businesses affected by these works will be notified closer to works commencing.

Name Town Type Of Work Road Number Date
Pacific Drive Eastbourne Surfacing Work U2573 Completed
Frant Green Road Frant Surfacing Work A267 March 2025
Bartley Mill Road Frant Surfacing Work C82 Completed
St Johns Road St Leonards Surfacing Work U3158 30/09/2024
Githa Road Hastings Surfacing Work U3225 Completed
Holliers Hill Bexhill Surfacing Work B2182 11/03/2024
Harbour Road Rye Concrete Road Work C98 Completed
Rose Walk Close Newhaven Concrete Road Work U5277 Completed
Evelyn Road Lewes Concrete Road Work U5107 Completed
The Drive Hailsham Concrete Road Work U7716 Completed
Westville Road Bexhill Concrete Road Work U6562 17/04/2024
Westville Road Bexhill Concrete Road Work U6562 12/08/2024
Newlands Avenue Bexhill Concrete Road Work U6587 Completed
Knowle Road Fairlight Concrete Road Work U6184 Completed
Heather way Fairlight Concrete Road Work U6186 Completed
Woodland Way Fairlight Concrete Road Work U6184 Completed
Camperdown Street Bexhill Concrete Road Work U6593 Completed
Knowle Road Fairlight Concrete Road Work U6184 Completed
Newlands Avenue Bexhill Concrete Road Work U6587 Completed
Pembury Grove Bexhill Concrete Road Work U6593 24/07/2024
The Drive Hailsham Concrete Road Work U7716 27/08/2024
Chalvington Road Eastbourne Concrete Road Work U7216 09/09/2024
Gorringe Valley Road Willingdon Concrete Road Work U7756 16/09/2024
Cranston Rise Bexhill Concrete Road Work U6533 30/09/2024
Southdown Avenue Lower Willingdon Concrete Road Work U7740 04/10/2024
Evelyn Road Lewes Concrete Road Work U5107 21/10/2024
Fuller Road Lewes Concrete Road Work U5107 November 2024
Harbour Road Rye Concrete Road Work C98 November 2024
Rose Walk Close Newhaven Concrete Road Work U5277 November 2024
Meads Brow Eastbourne Crack and Jointing Work U2003 Completed
Montacute Road Lewes Crack and Jointing Work U5103 Completed
Rocks Park Road Uckfield Crack and Jointing Work U7776 Completed
Kitchenham Road Catsfield Crack and Jointing Work A271 19/03/2024
The Gorses Bexhill Crack and Jointing Work U6543 Completed
Parkstone Road Hastings Crack and Jointing Work U3029 02/04/2024
Standard Hill Ninfield Crack and Jointing Work A269 Completed
Kingfisher Drive Eastbourne Patching Work U2220 Completed
Chyngton Gardens Seaford Patching Work U5411 Completed
Lephams Bridge Road Uckfield Footway Work A272 Completed
Drove Road Newhaven Footway Work A259 Completed
Station Road Heathfield Footway Work C273 Completed
Highlands Avenue Uckfield Footway Work U7773 Completed
Collier Road Pevensey Footway Work U7287 Completed
Church Marks Lane East Hoathly Footway Work U7024 Completed
Richmond Road Pevensey Footway Work U7728 Completed
Church Marks Lane East Hoathly Footway Work U7024 Completed
Iveagh Crescent Newhaven Footway Work U5103 Completed
Green Lane Crowborough Footway Work B2157 Completed
Highlands Avenue Uckfield Footway Work U7773 Completed
Sea Road Winchelsea Footway Work C92 Completed
Eastbourne Road (east) Pevensey Footway Work A259 Completed
Eastbourne Road (west) Pevensey Footway Work A259 Completed
Eridge Road Crowborough Footway Work A26 14/05/2024
Rotherfield Road Crowborough Footway Work B2100 09/09/2024
Eridge Road Crowborough Footway Work A26 11/09/2024
Fairlight Field Ringmer Footway Work U5681 16/09/2024
Drove Road Newhaven Footway Work A259 18/09/2024
Station Road Heathfield Footway Work C273 23/09/2024
Rotherfield Road Crowborough Footway Work B2100 30/09/2024
Station Approach Heathfield Footway Work C273 04/10/2024
Thorny Close Heathfield Footway Work U7351 07/10/2024
West Street Alfriston Footway Work U7726 October 2024
Green Lane Crowborough Footway Work B2157 November 2024
Green Lane Crowborough Footway Work B2157 November 2024
School Lane (Greenacres) Heathfield Drainage Work C406 Completed
School Lane (Greenacres) Heathfield Drainage Work C406 Completed
School Lane (Greenacres) Heathfield Drainage Work C406 February 2025
Mayfield Road Five Ashes Drainage Work A267 January 2025
Highcroft Crescent (Wren Close) Heathfield Drainage Work U7064 December 2024
Withyham Road Groombridge Drainage Work B2110 Completed
Withyham Road Groombridge Drainage Work B2110 February 2025
Station Road Buxted Drainage Work A272 Completed
Station Road Buxted Drainage Work A272 February 2025
Winterbourne Mews Lewes Drainage Work B2110 Completed
The Green Sedlescombe Surfacing Work B2244 Completed
Cherry Gardens Hill Groombridge Surfacing Work B2188 Completed
South Road Hailsham Surfacing Work A295 Completed
Bunny Lane Frant Surfacing Work C70 Completed
Crowborough Hill - Pipe Lining Crowborough Drainage Work B2100 Completed
A22 (Lewes Road) Forest Row Drainage Work A22 Completed
London Road Forest Row Surfacing Work A22 Completed
Station Road Robertsbridge Surfacing Work C18 Completed
Bayham Road (Bells Yew) Frant Drainage Work B2169 May 2025
Church Lane Pevensey Drainage Work U7707 Completed
Church Lane Pevensey Drainage Work U7707 Completed
Church Lane Pevensey Drainage Work U7707 Completed
Grand Parade St Leonards Drainage Work A259 Completed
Lewes Road Blackboys Drainage Work   December 2024
Lewes Road Blackboys Drainage Work   April 2025
Westcourt Drive Bexhill Drainage Work U6536 Completed
Westcourt Drive Bexhill Drainage Work U6536 January 2025
Wadhurst Road Mark Cross Drainage Work B2112 February 2025
High Street Ticehurst Drainage Work B2112 November 2024
Station Road Wadhurst Drainage Work U6536 Completed
Station Road Wadhurst Drainage Work U6536 March 2025
Diplocks Way Hailsham Surfacing Work U7221 Completed
High Street Burwash Surfacing Work A265 March 2025
Hailsham Bypass Hailsham Crack and Jointing Work A22 Completed
High Street Maresfield Surfacing Work C33 November 2024
Frant Green Road - Drainage Frant Drainage Work A267 November 2024
North Trade Road - Drainage Battle Surfacing Work A271 Completed
North Trade Road Battle Surfacing Work A271 23/09/2024
Westcourt Drive Bexhill Surfacing Work U6536 March 2025
Newhaven Road - Drainage Rodmell Surfacing Work C7 07/10/2024
Newhaven Road Rodmell Surfacing Work C7 February 2025
East Street Seaford Surfacing Work C36 14/10/2024
Lewes Road (A26 Bend) - Drainage Little Horsted Surfacing Work A26 Completed
Lewes Road (A26 Bend) Little Horsted Surfacing Work A26 Completed
Broom Lane Frant Surfacing Work U7841 November 2024
Junction Road Bodiam Surfacing Work B2244 February 2025
Rodmell Drive Eastbourne Surfacing Work U2103 March 2025
Pett Level Road - Drainage Pett Surfacing Work C92 Completed
Pett Level Road Pett Surfacing Work C92 30/09/2024
Ringmer Road Ringmer Patching Work B2192 21/10/2024
Uckfield Road Herons Ghyll Patching Work A26 October 2024
Eridge Road Frant Patching Work A26 November 2024
Uckfield Road Herons Ghyll Patching Work A26 November 2024
Burwash Rd Heathfield Patching Work A265 November 2024
Cackle Street Brede Patching Work A28 January 2025
Five Chimneys Hadlow Down Patching Work C270 October 2024
Hartfield Rd Forest Row Patching Work B2110 November 2024
High Street/Lewes Rd Blackboys Patching Work B2192 / B2102 November 2024
The Village Alciston Patching Work U7722 November 2024
Bardown Rd / Stonegate Rd Stonegate Patching Work C214 December 2024
Hastingsford Lane Hadlow Down Patching Work C11 21/10/2024
Church Hill / Black Hill Crowborough Patching Work B2188 November 2024
Hammer Hill / Church Rd Ashburnham Patching Work C18 November 2024
Hammer Hill / Church Rd Ashburnham Patching Work   January 2025
Tunbridge Wells Rd Mark Cross Patching Work A267 March 2025
Frant Rd Frant Patching Work A267 March 2025
Mayfield Rd Frant Patching Work A267 March 2025
Lower High St (Moseham Hill) Wadhurst Patching Work B2099 July 2025
Lewes Road Forest Row Crack and Jointing Work A22 January 2025
Falaise Road Hastings Footway Work U3161 January 2025
Mount Pleasant Road Hastings Footway Work C457 January 2025
Priory Rd Hastings Footway Work U3186 February 2025
Harold Rd Hastings Footway Work U3214 February 2025
Saxon Rd Hastings Footway Work U3214 March 2025
Old London Rd Hastings Footway Work A259 March 2025
Ashburnham Rd Hastings Footway Work U3224 March 2025
Battle Road Heathfield Footway Work B2096 April 2025
Battle Road Punnetts Town Footway Work B2097 April 2025