Map of works area
Balfour Beatty is working in partnership with East Sussex County Council to manage the highway service across East Sussex. As part of this, we will be upgrading the traffic signals on North Way, Newhaven.
When do they start?
Works will be carried out from Monday 3 November to Friday 21 November 2025 between 7am and 5pm. We will inform you of any changes to the dates or times via advanced warning signs on site.
We plan to complete similar works in South Way in the new year, with more information being provided in due course.
What are we doing?
These works involve the removal of the current traffic signal equipment and installing new upgraded traffic signals and crossing points. This will improve road safety in this area.
How will this impact highway users?
The road will remain open with a lane closure in place to minimise any disruption.
Information for residents and businesses
Parking: We will put out ‘no parking’ signs and cones on the site to advise where parking is restricted. Please avoid parking in these locations as it will delay our work.
Weather: All of these works are subject to favourable weather conditions, for example heavy rain may affect the progress of the works.
Properties close to the carriageway may experience a temporary disturbance as this can be a noisy process. There may also be flashing lights and reversing sirens.
We would like to take this opportunity to apologise in advance for any inconvenience or disruption this work may cause, however this forms part of our continuing improvement for the East Sussex highway network. Should you have any concerns regarding these works, you can contact us at eshcomms@balfourbeatty.com.
Please let us know how we did by leaving feedback. Please note you will be redirected to the East Sussex County Council consultation website.
One.Network Permit reference - EA44462491660-03 & EA44448568065-04.