C19 Bodiam Road, Hurst Green - Carriageway works

Map of works area

Map of works area

We’ll soon be carrying out carriageway repairs and resurfacing works, to improve the overall condition of the carriageway.

When do they start?

Work will be carried out from Monday 16 November to Saturday 5 December 2026, 7pm - 6am.

We will inform you of any changes to the dates or times via advanced warning signs on site.

How will this impact highway users?

We will be working between the junctions of the A21 and the B2244.

The road will be closed to through traffic during our working hours, with a signed diversion route in place via the A229, the A21, the B2244, and vice versa.

For safety, access to properties within the works area will be limited and managed during our working hours. If you need access, please speak to the team on site. Please bear in mind, there could also be a delay while the area is made safe for you to pass and your vehicle may be escorted by site marshalls. This is for properties with direct access within the closure area only and there will be no through route.

Please be polite and respectful to the site teams, they are working to keep everyone safe. Thank you for your patience while we carry out these improvements.

Information for residents and businesses

Parking: If required, we will put out ‘no parking’ signs and cones on the site to advise where parking is restricted. Please avoid parking in these locations as it will delay our works.

Weather: All of these works are subject to favourable weather conditions, for example heavy rain may affect the progress of the works.

Properties close to the carriageway may notice some noise, flashing lights, or reversing sirens. We will do our utmost to keep this to a minimum.

We would like to take this opportunity to apologise in advance for any inconvenience or disruption this work may cause, however this forms part of our continuing improvement for the East Sussex highway network. Should you have any concerns regarding these works, you can contact us at eshcomms@balfourbeatty.com.

We would like to take this opportunity to apologise in advance for any inconvenience or disruption this work may cause, however this forms part of our continuing improvement for the East Sussex highway network.

Feedback Form

One.Network Permit references - EA101HM-0390A-02, EA101HM-0390B-02, EA101HM-0390C-02